Use this suggested sequence to organise implementation. It is a clinic project plan, not an automatic onboarding workflow or a guaranteed two-week delivery commitment.

Week 1: prepare the operating model#

  1. Clinic identity and branches: confirm the tenant, currency, branch records, and authorised staff.
  2. Catalog: prepare the services, products, prices, packages, and accountant-reviewed tax setup.
  3. Capacity: configure session sources and provider availability, then check real calendar slots.
  4. Roles: assign staff roles and branches. Verify subscribed features with ordinary staff accounts.
  5. Accounting: review account mappings, payment methods, and opening balances. Accounting → Daily close provides the supported shift close and approval workflow; a Cash deposits staff page and Z-report PDF are not available.
  6. External services: start channel, gateway, and exchange onboarding early. Approval times and provider readiness are outside the calendar plan.

Week 2: rehearse and resolve gaps#

  1. Use a test environment with synthetic patient data and implementation-approved integration settings.
  2. Rehearse booking, readiness, arrival, clinical recording, material usage, and discharge with each relevant role.
  3. Verify the invoice, package balance, stock, payment, and accounting entries individually.
  4. Exercise cancellation, no-show, a partial credit/refund, and a rejected or missing message where relevant.
  5. Confirm the clinic's manual continuity procedure and named support contacts.
  6. Agree the live cutover only after the responsible clinical, operations, and accounting contacts accept the results.

Go-live review#

Record the environment and integration configuration used for testing. A sandbox checkout alone does not prove all other outbound services are isolated. Do not promise receipt delivery, clinical exchange acceptance, or settlement solely because the initial action saved successfully.