Use this suggested sequence to organise implementation. It is a clinic project plan, not an automatic onboarding workflow or a guaranteed two-week delivery commitment.
Week 1: prepare the operating model#
- Clinic identity and branches: confirm the tenant, currency, branch records, and authorised staff.
- Catalog: prepare the services, products, prices, packages, and accountant-reviewed tax setup.
- Capacity: configure session sources and provider availability, then check real calendar slots.
- Roles: assign staff roles and branches. Verify subscribed features with ordinary staff accounts.
- Accounting: review account mappings, payment methods, and opening balances. Accounting → Daily close provides the supported shift close and approval workflow; a Cash deposits staff page and Z-report PDF are not available.
- External services: start channel, gateway, and exchange onboarding early. Approval times and provider readiness are outside the calendar plan.
Week 2: rehearse and resolve gaps#
- Use a test environment with synthetic patient data and implementation-approved integration settings.
- Rehearse booking, readiness, arrival, clinical recording, material usage, and discharge with each relevant role.
- Verify the invoice, package balance, stock, payment, and accounting entries individually.
- Exercise cancellation, no-show, a partial credit/refund, and a rejected or missing message where relevant.
- Confirm the clinic's manual continuity procedure and named support contacts.
- Agree the live cutover only after the responsible clinical, operations, and accounting contacts accept the results.
Go-live review#
Record the environment and integration configuration used for testing. A sandbox checkout alone does not prove all other outbound services are isolated. Do not promise receipt delivery, clinical exchange acceptance, or settlement solely because the initial action saved successfully.